APMG-International Agile Project Management (AgilePM) Practitioner AgilePM-Practitioner Exam Questions
Question #1 (Topic: demo questions)
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
Correct Answer: B, E
Explanation:
In the context of Agile Project Management when developing the Prioritised Requirements List during Feasibility, the two statements that align with Agile principles are: B . The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements. E. Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements. Here's the rationale: • B: In Agile, requirements are often categorized by priority such as "Must Have", "Should Have", "Could Have", and "Won't Have for now" (the MoSCoW method). The re-laying of the driveway and a landscaping solution are essential for the project's success and thus should be classified as "Must Have". • E: Regulatory requirements are non-negotiable constraints that the project must adhere to. These should always be prioritized in the requirements list to ensure compliance and to avoid legal issues, making them "Must Have" items as well.
Question #2 (Topic: demo questions)
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the number of selections requested in each question. Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
Correct Answer: A, C
Explanation:
In the context of Agile Project Management when developing the Solution Architecture Definition (SAD), the two statements that are appropriate are: A . Paper-based drawings are to be used for each option being considered for the building and gardens. C . The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution. Here's the rationale: • A: Agile methodologies support the use of simple and understandable tools that can quickly convey ideas and be easily changed. Paper-based drawings align with this by providing a flexible and adaptable way to represent different options, which can be rapidly modified in response to feedback. • C: It is important for the Marketing Director, who understands the market and customer needs, to request clarification on complex elements to ensure that the proposed solutions are feasible and aligned with customer expectations. This contributes to creating a solution that is viable both technically and from a business perspective.
Question #3 (Topic: demo questions)
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the number of selections requested in each question. Which 2 statements describe the appropriate application of Agile Project Management when developing the Delivery Plan?
Correct Answer: A, E
Explanation:
In the context of Agile Project Management, when developing the Delivery Plan during the Feasibility phase, the two statements that best align with Agile principles are: A . The Project Manager should include any known constraints associated with planning permission. E . The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan. Here's the rationale: • A: Recognizing and accounting for known constraints such as planning permission is a key aspect of Agile. It allows for better adaptability and planning around these constraints. Including them early in the Delivery Plan helps ensure that they are considered throughout the project. • E: Agile emphasizes cross-functional collaboration and stakeholder engagement. The Marketing Director would provide valuable insights into customer needs and market conditions, which are crucial for a successful delivery plan.
Question #4 (Topic: demo questions)
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility. Remember to limit your answers to the number of selections requested in each question. Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
Correct Answer: B, C
Explanation:
In applying Agile Project Management to the creation of an Outline Business Case in support of the Feasibility Assessment, the following two statements are most appropriate: B . Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed. Agile approaches favor providing just enough detail to make informed decisions without going into unnecessary depth at early stages. This allows for flexibility and adaptation as more information becomes available. C . During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.
Question #5 (Topic: demo questions)
UsingtheProjectScenario and the additional information provided for thisquestionintheScenario Booklet, answer the following questions about Feasibility. Remembertolimityour answers to the number of selections requested in each question. Which2statementsdescribe the appropriate application of Agile Project Managementwhendeveloping the Feasibility Assessment?
Correct Answer: B, D
Explanation: